We will be moving forward with the Cabana Project this week.
  1.  Carrie will confirm that we have the final drawings for the building dept. These will need to be stamped by an engineer.
  2.  We will need a meeting with the plumber to go over the plumbing that will be installed through the slab.
  3.  We will need a meeting with the electrician to go over lighting options and desires.
  4.  Ross will set up meeting with site-work guys to discuss logistics. Cabana foundation. Pool. Main house foundation.
  5.  Peter and Mike will discuss carpentry finishes and processes. Currently we are considering board and batten siding, barn board cabinets, Gas fireplace, exposed beams, metal roofing, exposed rafter tails and more.
  6.  We will put together a schedule this week.